Project updates: Throughout the month of December work will continue by Artesian on Tilney Street and Mulberry Street to complete wastewater infrastructure installation; a portion of Tilney Street will be closed to through traffic. The Towns project of water main work in the area of Mill Street and Walnut Street also continues into December. Street sweeping will take place 12/4 and the week of 12/15-12/18. Please avoid parking on the street to allow a clear path for the street sweeper. CodeRed is unavailable at this time. Updates will be posted on the town website. To register for CodeRed, please see the following link. More Info